Time is running out for many organisations with just eight years before The Climate Neutral Data Centre Pact (CNDCP) comes into force, according to Simon Harris, Head of Critical Infrastructure at BCS (Business Critical Solutions), who believes that many are not ready.

“The sector has had an extremely challenging couple of years with the impact of Covid 19 and the increasing demands for data as global computing capacity continues to rapidly increase. It is therefore entirely understandable that some organisations may have been focussed on other areas as 2030 seems a long way away – however there is significant work to be done!”

By 1st January 2030 CNDCP requires signatories to make a binding commitment to achieve Power Use Effectiveness (PUE) of between 1.3 and 1.4 in sites built up to 2025. It has been estimated that around 60% of data centres in Europe are in excess of eighteen years old.

“Amongst these the older data centres will have often been constructed with PUEs of 2.0 or more. In their current form they could be significantly distant from the required standard and in breach of their owners CNDCP commitments. They will also look increasingly unattractive to tenants pursuing socially responsible energy and carbon agendas. These operational sites will be challenging to upgrade, especially those with high availability requirements. They will require experienced design and construction teams, working closely with operational teams, in order to effect the changes to the engineering infrastructure that are required without service interruption,” explains Simon.

Advertisement

The simplified response to this problem may be to demolish and reconstruct at a convenient point before the deadline through a managed vacation and migration of IT processing. However, is not necessarily the best answer according to Simon as the original design and financial plans for these sites were often authored with the structural and architectural elements having a life expectancy of sixty years.

“There is also a significant embodied carbon penalty to pay in demolition and rebuilding. A substantial amount of the construction work involves the use of energy dense concrete and steel to such an extent that refurbishing an existing facility can save in the order of 70% – 80% of the carbon cost of a new build. An upgrade and refresh to critical infrastructure could liberate trapped electrical capacity for deployment to serve higher density and growing IT loads, for example through UPS replacement or cooling solution changes. These types of interventions will be more easily accommodated in Tier III facilities having two concurrently maintainable power and cooling paths, although the work will require careful planning and right first time execution. Nevertheless, such a solution overcomes the power availability challenges and takes the facility down a path towards better PUE performance,” he adds.

However, the PUE thresholds are not the only challenge embedded within the CNDCP.  The pact requires data centre electricity demand to be matched by 75% renewable energy or hourly carbon-free energy by the end of 2025 and 100% by end 2030. This, according to Simon, is particularly challenging as these requirements are to be delivered in a period when demand for renewable resources will be universally increasing as a result of competing demands from the growth in big data, the decarbonisation of industry, commerce, transport and domestic consumers.

“The good news is that at BCS we have seen significant energy efficiency improvements delivered as part of a general refreshment of assets that are beyond their economic life. We believe that there is still time for organisations to successfully achieve the targets for CNDCP but the clock is ticking…”

Advertisement